Is it a good idea to wait until the floors are installed before installing the doors or should the doors be installed first or doesn t it matter.
Prehung door before or after finished floor.
This is for timing.
I removed old wood walls and putt in new drywall and so now the door frame is off balance with the wall.
Before the floors go in you can easily shim one end of the jamb to get the door exactly plumb.
So i need to buy new prehung interior doors.
After floors this would be a huge pain to do since you would need to pull the door out and saw the jamb.
By having all the doors and trim up first the painters can come in and spray everything out and get the first coat of color on the walls.
You should hang all doors and trim after dry wall.
The door jambs don t have to touch the subfloor in carpeted situations but they must be in contact with hardwood flooring ceramic tile cork or other finished floors that are typically smooth.
Then the flooring installers come in and do their thing.
Also maybe others are more careful but i found it s hard not to ding the floor a little bit when doing doors afterwards.
Just be sure to allow for a threshold or thick carpeting before making these cuts.
I love my doors which were installed today but since the floors were installed first i now have a gap or two where the new frame doesn t cover the flooring.
The clearance between the bottom of the door and the finish floor should be 3 8 inch or less.
Then you should paint all trim and doors first then ceiling and walls.
This clearance is set by trimming the ends of the hinge and latch jambs.
However we could do it.
Which project goest first.
Got laminate floors installed in july and then decided i wanted new interior doors.
Apparently so i learned this today the hard way.
But i also have to tile the floor.
Should the top and bottom of the door be painted.
This seals the.
After floors are in fenish with quarter round shoe molding.
I am gutting out the house and one project leads to another.
What i am looking to do is shim up the jamb to the desired height so that i will have 1 2 after carpet is installed and won t have to cut the doors.
We have the interior doors 6 panel doug fir purchased but it would be a push to get them in before the wood floor is installed.
Set the hinge side of doors 1 2 off floor to tuck in carpet.
I set the prehung unit and then remove the door until after carpet.
You can rent a saw that is special made for cutting door casings to allow tyle to go under.
The floors go in last.
Before the door is installed make sure the top and bottom of the door are painted.
Most builders leave the floors for last.
Baseboard goes down then the 2nd coat of paint goes on.
Check that the door will swing in the right direction after it s installed.